Talvar Project

TALVAR DAM & IRRIGATION NETWORK PROJECT
TALVAR WATER TRANSMISSION SCHEME

Project Purpose :


The main purpose of project is transmission of water from TALVAR DAM to TALVAR Plain for irrigation of fertilized canals of Mehrabad, Khorkhore & Chopoghloo area. Projects consists of 17.2 km canal in shape of Flave, Box and Trapezoidal canal as well as 9438m prestressed concrete pipe and 9400m steel pipe in 1800mm & 2000mm diameter. The capacity of water transmission line in 27cu.m. / sec.

Contractual Specification :
Client :
ZANJAN REGIONAL WATER AOUTHORITY

Consulting :
ABFAN-BOROO Joint Venture Consulting Engineers

Technical Specification :

  • Construction of 17.2km of concrete canal
  • Construction of 9.8km of drain
  • Construction of 3Nos. Siphone
  • Construction of Steel & Concrete pipeline 9400m. each.
  • Construction of 17.2km Service Road
  • Concrete works      51568 cu.m.
  • Earthworks              1547969 cu.m